June 17, 2025: Update on our ongoing projects and other miscellaneous items.
Pool Heaters
The contractor has all material and venting parts ready for installation. They are waiting on the permit being issued by the City of Miami Beach. The City’s system shows a scheduled permit issuance date of June 23, 2025
Transfer Switch Control Panel
The transfer switch control panel was successfully installed last week. To finalize the permit, we have obtained a proposal for an engineer to prepare the revised drawings and calculations. We are waiting to obtain at least a second proposal prior to approve the engineer work.
Elevator Repairs
Repairs have been completed and an inspection from the City of Miami Beach was conducted on June 16.
Concrete Restoration
We’ve successfully completed Phase II of the parking garage concrete restoration. Only Phases III and IV remain.
Our association attorney is diligently working to resolve billing discrepancies with Thornton Tomasetti (TT). We’ve reached out to the attorney multiple times for updates and were informed that TT no longer wishes to continue providing services for the project. We’re currently waiting for our attorney to provide the reasons behind TT’s decision.
In the meantime, the board has acknowledged this development and is actively interviewing other engineering firms to take over the project. We’re in the process of collecting proposals, which will be made available to all unit owners as soon as they’re received
Roof
Final inspection was conducted by the City on June 16 and it passed.
The roof permit and the mechanical permits are being closed.
Financials
The March and April financials are now available in the resident resources section. We do not have May financials yet
Gazebos
We have received a sample of the wood color material for the replacement of the gazebo floors. This sample will be available for review at the upcoming meeting, where we will solicit owner feedback and comments.
Management Position
Interviews for a new Property Manager are currently underway. The board intervied another candidate on June 17.
Improvements to Common Areas
- Pool Room Refrigerator: A new refrigerator for the Pool Room was delivered and it is now available for use.
- Sprinkler System (Planters): Repairs to the sprinkler system in the planters are completed.
- Carpet Cleaning: Semi-annual cleaning of all carpets on the 19th floor is scheduled for mid-June 2025
- Lobby painting: We are collecting a third proposal prior to move forward.
Impact Windows
Impact Doors for the Gym and Loobby area were delivered to AG and the installation of same will commence next week
as per AG notification on June 17, 2025
AC common areas
We obtained a 2nd estimate and are contacted a third company for the last estimate needed to make a decision
They will be discussed at the next meeting with the owners
We look forward to seeing many of you at the meeting during the week of [tbd]. Your feedback and participation are essential as we work together to make Oceanfront Plaza a first-class residence for all owners and guests.